Revision as of 23:19, 24 March 2013
Carousel 2013 | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Carousel
|
Carousel marks the second year of the large scale musical theatre performance within the Conservatoire.
Company
Creative Team
Director: Andrew Panton
Musical Director: Simon Beck
Choreographer: Emily-Jane Boyle
Associate Director: Susie Dumbreck
Set Designer: Alex Lowde
Lighting Designer: Simon Wilkinson
Sound Designer: Blair Omond
Projection Designer: Tim Reid
Technical Production Team
Stage Manager: Jack Hirst
Deputy Stage Manager: Amber McClelland
Assistant Stage Management:
Technical Stage Manager: Rebecca Coull
Chief Flyperson:
Stage Technicians:
Chief Electrician: Neil Foulis
Deputy Electrician: Audrey Wilson
Sound Designer/ Sound Number 1: Blair Omond
Sound Number 2: Laura Dougan
Lighting Operator: Audrey Wilson
Electricians:
AV Operator: Robert Butler
Sopt Operators: Keiran Fitzpatrick & Shannon Howard
Technical Stage Management
Electrics
LX Photos
LX Equipment
Generic Lamps
- SL 15-32 - 21
- SL 19* - 12
- SL 23-50 - 20
- SL 26* - 8
- 1.2K Fresnel - 33
- 1.2K PC - 2
- 2K Fresnel - 11
- 5K Fresnel - 1
- PAR 64 - 30 (10 CP 61, 20 CP 62)
- S4 PAR - 1
- Birdies - 11
- Coda FLood - 28
- Orion Groundrow - 8
Special Lighting Effects
- Vari Lite 1000 tsd - 4
- Reiche and Vogul Beamlights - 2
- Le Maitre MVS Hazer - 1
- Festoon 15M - 1
Festoon
Festoon was used to create a circus atmosphere, Because this was handled by the cast, it was required to be shatterproof. it took 30 x 40 Watt pearl Shatterproof bulbs for one 15M length of festoon.
These Bulbs were bought from a supplier called Covershield.
Lightbulb Halo
The Lightbulb Halo was a main part of the set, as it was the main element representing the Carousel.
My task was to wire up all 80 Lightbulbs in 4 circuits, so it could chase and look as though they were all chasing round the ring.
Firstly I found out the measurement between bulbs, (I used my Vectorworks plan to do this) and then made a template, see below.
I then laid out all the fittings where they go on the ring, and began wiring.
This was wired in Parallel, Each Live, and Neutral went in to the live and neutral points, and then out, and on to the next one. see explanation on Parallel wiring.
Final wiring in 4 circuits
Booms
all of the stage booms required to sit in line with the edge of the fly floor
unfortunately this meant they were sitting on the ramp up to the stage, So to solve this problem, we built small anti rakes to sit under the boom bases.
3 of the booms were to be 7 metres high, this was relatively easy to achieve, the 7M pole was tied to the fly floor, making them very rigid.